NovaCloud-Hosting - Migration to New Hardware and Network Infrastructure für Standard Root/Game Servers – Maintenance details
All systems operational
Migration to New Hardware and Network Infrastructure für Standard Root/Game Servers
Completed
Scheduled for 08 November, 2024 at 5:00 PM – 19 November, 2024 at 1:17 PM
Affects
SkyLink Data Center
Under maintenance from 5:00 PM to 1:17 PM
Game-Server Nodes EYG1
Under maintenance from 5:00 PM to 1:17 PM
EPYC-04
Under maintenance from 5:00 PM to 1:17 PM
Updates
Completed
19 November, 2024 at 1:17 PM
Completed
19 November, 2024 at 1:17 PM
Maintenance has completed successfully.
In progress
17 November, 2024 at 2:00 PM
In progress
17 November, 2024 at 2:00 PM
Wir übertragen XEON-01 Game-Host als letzten Teil der Wartungsarbeiten
Completed
10 November, 2024 at 5:00 PM
Completed
10 November, 2024 at 5:00 PM
Maintenance has completed successfully
Update
10 November, 2024 at 3:50 AM
In progress
10 November, 2024 at 3:50 AM
Standard Root-Server erfolgreich umgezogen
Wir haben nun alle Standard Root-Server umgezogen und diese sollten unter den neuen IPs nun erreichbar sein. Einige Features sind im Moment nicht verfügbar. Wir werden beides noch heute beheben:
NoVNC/Xterm.js
ISOs anhängen
Vielen Dank für euer Vertrauen in NovaCloud-Hosting. Wir hoffen mit dem Upgrade auf ein AMD EPYC 7543P Hostsystem drastisch die Performance und gleichzeitig die Stabilität zu verbessern. Bei Problemen öffnet bitte ein Ticket im Kundendashboard
Standard Game-Server werden im laufe des Tages umgezogen. Genaueres wird schnellstmöglich folgen. Bis dahin sind die Game-Server allerdings online.
In progress
08 November, 2024 at 5:00 PM
In progress
08 November, 2024 at 5:00 PM
Maintenance is now in progress
Update
08 November, 2024 at 5:00 PM
Planned
08 November, 2024 at 5:00 PM
We are migrating to new hardware and upgrading our network infrastructure with a new provider.
Due to several network-related outages with our current provider in recent months, we have decided to move our Intel Xeon customers to a new provider while significantly improving performance.
We are upgrading from Intel Xeon E5 2687W V4 to AMD EPYC 7543P processors, and replacing SATA SSDs with NVMe SSDs, offering a performance boost of up to 300%.
The entire migration process will take approximately 24-48 hours. Each customer will experience downtime ranging from 10 minutes to 1 hour, depending on the size of their root server.
Standard Game server customers should expect around 1 hour of downtime.
Please note that all IP addresses for root servers and standard game servers will change. Be sure to retrieve your new IP address from the dashboard.
Update
08 November, 2024 at 11:00 AM
Planned
08 November, 2024 at 11:00 AM
Da die Hardware vom Lieferanten noch nicht angekommen ist, müssen die Wartungsarbeiten verschoben werden.
Neues Datum: 06.11.2024 (Falls die Hardware bis zu dem Zeitpunkt nicht eingebaut ist kann es sich weiter verzögern)
Planned
07 November, 2024 at 12:57 PM
Planned
07 November, 2024 at 12:57 PM
Da die Hardware vom Lieferanten noch nicht angekommen ist, müssen die Wartungsarbeiten verschoben werden.
Neues Datum: 08.11.2024 (Falls die Hardware bis zu dem Zeitpunkt nicht betriebsfähig ist kann es sich weiter verzögern)